Blackburn Town Centre - Site Acquisition and Masterplan

Decision Maker: Executive Board

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

(1)        That it be noted the former Thwaites Brewery site represents a major development opportunity and was of key strategic importance to Blackburn Town Centre.

 

(2)        That it be noted that Maple Grove Blackburn Ltd., the joint venture company between the Council and Maple Grove Developments Ltd., had acquired the former Thwaites Brewery site in 2021, for the purpose of preparing the site for future development.

 

(3)        That the withdrawal of the food store relocation planning application in March 2024, which subsequently instigated a review of the joint venture company arrangements with the recommendations to acquire control of the company and therefore control of the Site, be noted.

 

(4)        That the purchase of Maple Grove Developments Ltd., financial interest in the joint venture company for the Purchase Price be approved to ensure the Site was delivered as part of a robust masterplan to ensure future development would deliver positive outcomes for the town centre.

 

(5)        That the revised terms for a 3-year non-exclusive option agreement to Maple Grove Developments Ltd., be approved to acquire a parcel of land as identified on the plan attached at Annex 2, which would support Building 2 being brought forward as a speculative scheme which was part of the Council’s emerging Skills and Cyber campus.

 

(6)        That subject to compliance with the Council’s Financial procedure Rules in relation to Purchase of Land and Buildings, a capital spend of up to £1,000,000 be approved to cover further land assembly enabling works and masterplan activities and it be noted that this funding would be drawn down from the existing Development Investment fund and therefore required no additional funding.

 

(7)        That the Council’s Contract Procedure Rules be waived and BDP Architects be appointed to commence work on revising the Town Centre East Development Framework document, published in 2021, to create a robust masterplan for the Blackburn Town Centre East Investment area, and it be noted the Council will consult on a draft of the revised masterplan for the town centre in 2025.

 

(8)        That delegated authority be granted to the Growth Programme Director, in consultation with the Strategic Director Finance and Resources and Deputy Director of Legal and Governance to agree final terms for the acquisition of Maple Grove Developments Ltd., financial interest in the joint venture company; and all associated legal, financial, administrative and management arrangements of the company.

 

Publication date: 15/11/2024

Date of decision: 14/11/2024

Decided at meeting: 14/11/2024 - Executive Board

Effective from: 22/11/2024