Growth Deal 3 - South East Blackburn

To Update on progress made with Growth Deal 3 South East Blackburn major transport scheme package, to accept main contractor prices and to agree to the application for Full Approval being made to the Lancashire Enterprise Partnership.

Decision type: Key

Reason Key: Affects more than 1 ward;

Decision status: Recommendations Approved

Wards affected: Audley & Queens Park; Blackburn Central; Blackburn South and Lower Darwen; Blackburn South East;

Notice of proposed decision first published: 11/10/2019

Decision due: 14 Nov 2019 by Executive Board

Lead member: Executive Member for Growth and Development

Lead director: Strategic Director of Growth & Development

Department: Growth and Development

Contact: Mike Cliffe Email: mike.cliffe@blackburn.gov.uk.

Consultation process

Two public exhibitions took place on the project in late January / early February 2019, and feedback has been fed into the scheme and design.

Planning Applications have also been submitted (Haslingden Road 10/19/0887 and Blackamoor Rad 10/19/0888) and will be considered by the Council's Planning Committee in December 2019.

Making Representations: Mike Cliffe, Strategic Transport Manager x 5310

Comments: Documents considered: 8th March 2018 Executive Board - Pennine Gateways Project 11th April 2019 Executive Board - Local Transport Plan Programme 2019/20